See this article if you first want to learn about the planning and how parallelization works.
This article explains how to set up a parallelized system with several battery storage units correctly. The focus is on the required settings on the inverter for 2-way parallelization, supplemented by notes on wiring, minimum distances and expanding existing systems.
The explanations in the video additionally support the implementation. We recommend watching the videos beforehand. The step-by-step instructions below describe the settings shown in the video in written form.
Step-by-step instructions: settings on the hybrid inverter for 2-way parallelization
Before a 2-way parallelized system (with BMS variant V2 for STAAK) can be commissioned, the steps from chapters 12.1 to 12.4 of the manual must be completed.
Then make the following settings on the hybrid inverter:
1. Open advanced settings
- Select the menu Advanced settings ("Erweiterte Einstellungen").
- Enter the password 0001.
2. Configure battery settings
Configure the battery settings for two parallelized battery storage units according to the following parameters:
Parameter | STAAK | STAAK Eco |
|---|---|---|
Maximum charge current | 50.0 A | 37.0 A |
Maximum discharge current | 50.0 A | 37.0 A |
You can find the values under Advanced settings > battery parameter.
Note: 50.0 A is the highest charge and discharge current of the NEEO (two battery inputs with up to 25 A each). From firmware V116462, the NEEO detects the battery modules itself and sets the battery current to a maximum of 50 A. The BMS always defines the limit: a higher value on the inverter does not exceed it.
3. Save the settings
- After entering all values, select "Save" ("Speichern").
Expanding existing systems
If you want to expand an existing system, please note:
- Expanding with additional inverters or battery storage units requires coordination with an electrician or neoom customer support.
- For planning, the manual chapters 5.5 "Cascading" and 5.6 "Parallelization" are relevant.
- If necessary, the existing system must be decommissioned again according to chapter 16.
Completion and test operation
After completing the wiring and the settings:
- Check the connection of all systems.
- Check the synchronization of the battery storage units.
- Start test operation and check for any error messages.
- If in doubt, contact technical support.